Gurugram: Land hurdle holds up revamp of Hero Honda Chowk-Umang Bhardwaj Chowk stretch | Gurgaon Information

[ad_1]

GURUGRAM: Six months after the challenge’s launch, work to revamp the stretch between Hero Honda Chowk and Umang Bhardwaj Chowk within the metropolis is but to start. The problem – issues in demarcation of land that’s holding up development.
The challenge includes constructing an underpass on the Khandsa crossing and a flyover on the Umang Bhardwaj Chowk to ease site visitors motion on the 2km-stretch.

download (2)

“The Haryana Shahari Vikas Pradhikaran (HSVP) was presupposed to demarcate the land and provides it to us, however some points have cropped up. We’re engaged on resolving these. As soon as this downside is sorted, we’ll begin utility shifting,” stated a senior NHAI official stated on Friday. Utility shifting implies transferring utilities equivalent to underground pipelines, electrical cables, or electrical poles that fall on the alignment of the challenge. They’re usually shifted earlier than development work begins. The Nationwide Highways Authority of India (NHAI) is liable for the development, which is a component of a bigger challenge.
Demarcation includes figuring out precisely how a lot land might be required for the event work, permitting authorities to plan the challenge accordingly. In circumstances the place personal land must be acquired, it additionally permits landowners to higher perceive how a lot land they might have to surrender.
When requested, an HSVP official stated there have been some minor obstacles, together with {an electrical} sub-station on the stretch, that had been delaying the method.
This delay in finishing demarcation work means no work has begun on the bottom although the challenge was formally launched in November final 12 months.
NHAI, nevertheless, continues to be hopeful of having the ability to meet the November 2023 deadline.
“The challenge is transferring not on time as of now, however we don’t anticipate this to impression the ultimate deadline. Points usually crop up within the preliminary levels of a challenge however as soon as work begins, it tends to proceed easily. We’re nonetheless hopeful that, as soon as development begins, we will make up for the delay,” stated the official cited above.
The revamp of the 2km stretch is a part of a wider challenge to ease motion between the Hero Honda Chowk and the Dwarka Expressway with the development of two flyovers, a railway overbridge, and an underpass. Roads too might be widened in some areas.
NHAI will perform development on the 2km stretch, which is crucial because it gives connectivity between Basai, Dwarka Expressway, Pataudi highway and Nationwide Freeway 48 – all of that are key routes for town’s residents.
The remaining 3.6 kilometres between Umang Bhardwaj Chowk and the expressway might be revamped by the Gurugram Metropolitan Improvement Authority (GMDA). This contains constructing the second flyover, at Basai Chowk, and the railway overbridge close to Basai village.
The a part of the challenge to be managed by GMDA started development in 2018, and work is anticipated to be accomplished subsequent month.
NHAI’s work, nevertheless, was held up as a result of the physique altered the preliminary development plan and clubbed it with one other bigger challenge to construct a freeway between Pataudi and Rewari.